Hunt County weekly road report || August 26, 2024
-
SH 34, from FM 1570 to FM 2101. The contractor has set barricades and work zone signs. The contractor has completed the flexible pavement repair on the main lanes and shoulders. The contractor has finished the placement of HMA overlay on the northbound and southbound lanes. The contractor has finished placing final striping and has completed backfilling pavement edges throughout the project. Seeding and mulch has been placed and watering has started. Please be aware of workers and watch for work zones when traveling in this area.
- SH 11, from FM 2655 to SH 24. This project will add shoulders and replace drainage structures. The contractor has set barricades and has begun some prep right of way work and has begun road widening and ditch grading in the area. SW3P devices will be installed soon. The contractor has placed SW3P devices and prepped the right of way. Culvert work on the project and excavation and road widening is in progress. Please be aware of workers and watch for work zones when traveling in this area.
- SH 11, from Culver Street to Live Oak. The contractor has placed work zone signs and barricades. Fencing installation and grate work is ongoing. Final signal work is underway, barrels and barricades have been removed to open lanes. Final punch list items are underway. Oncor is working to supply power to the signal lights. Please be aware of workers and watch for work zones when traveling in this area.
- FM 1563, from SH 50 to SH 2655: This is a 2.7-mile rehabilitation project that will widen the existing roadway. The contractor has set work zone signs and barricades. The contractor has completed cross culverts and culvert extensions and will be placing riprap soon. The contractor has sealed and shouldered up the first mile of the project and has placed flex base and placing geogrid at various locations. Driveways are ongoing and are being completed by section of work. Please be aware of workers and watch for work zones when traveling in this area.
- FM 2642, from FM 35 to SH 66: The contractor has set work zone signs and barricades. Excavation work for the detour is ongoing. The contractor has been working on the placement of storm sewer and culverts will continue along FM 2642 north of I-30 towards SH 66 with embankment and excavation work. Nighttime operations are currently being used for several cross-culvert locations. The contractor is placing geogrid and flex base on FM 2642 near Royse City high school moving north. The contractor placed barrier and crash cushions on FM35. Please be aware of workers and watch for work zones when traveling in this area.
- FM 2649, from I-30 to FM 1567. The contractor has set barricades and work zone traffic signs. Cross culvert work is complete. The contractor has begun work on the final section of roadway, this work will begin with subgrade widening and treating the subgrade and vegetation establishment. Driveway pipes were being installed along with striping for the completed section. Grading and seeding will be completed soon. Please be aware of workers and watch for work zones when traveling in this area.
- I-30 intersection improvements from Monte Stratton to FM 1903. The contractor has set barricades and advance warning signs. The westbound I-30 main lanes have been realigned to detour paving around the existing westbound I-30 main lane bridge over FM 1570. This detour will remain in place until the new FM 1570 overpass is constructed. Detours are in place for NB and SB FM 1570 traffic around the closure. The westbound frontage road at FM 1903 is one-way only along with the frontage roads along the project corridor. Traffic on FM 1903 from north of I-30 will have to turn right on the westbound frontage road and travel to State Highway 36 in order access I-30 east. The contractor plans to place more barriers and perform main lane widening and drainage work in the area. Please be aware of workers and watch for work zones when traveling in this area.
- I-30 Improvements from CR2511 to FM 36: The contractor is currently grading and placing embankment between the frontage roads and mainlanes. Culvert work is ongoing. Paving for detours near FM 1565 exit has started, please be aware oof workers in the area. Contractor will be placing low profile barrier on the EB frontage road near FM 1565
- Hunt and Rains Counties Hunt County and Rains maintenance crews will be performing pothole repair work throughout Hunt and Rains County. Hunt County MNT will be overlaying FM 118 and US 69 and I-30 frontage road near SH 34. Rains County maintenance crews will continue to perform seal prep and patch on FM 513 and perform culvert work on FM 1564.